US West - Upstream Networking Issues
Incident Report for Arcustech, LLC
Resolved
This incident has been resolved.
Posted Jun 14, 2021 - 21:57 CDT
Monitoring
The data center's power issues have been corrected, and impact to our network traffic has been returned to normal activity. We will leave this in "Monitoring" for about 15 to 20 minutes just to make sure, and then will auto set this incident to "Resolved".

If you are still having any issues, please let our support team know.
Posted Jun 14, 2021 - 21:19 CDT
Identified
Looks at though the primary cause is some A and B power circuit outages in certain data halls in our providers data center. This is likely causing impacts to the before mentioned core router, but likely some of the switching equipment between our racks and the data centers core network. At the moment our own equipment does not seem to be affected by this loss of primary and secondary power circuits.
Posted Jun 14, 2021 - 20:42 CDT
Update
We are awaiting further updates but seems the issue is come from issues on one of our data center providers core routers. Again once we have more details we will update this incident.
Posted Jun 14, 2021 - 20:37 CDT
Investigating
Staff are seeing random reports from our external monitoring about trouble reaching certain clients/ip ranges in our US West (Fremont, CA) data center location. Staff are working with our data center/upstream provider in Fremont to identify the issues on their network currently. We will update as soon as we have more details.
Posted Jun 14, 2021 - 20:16 CDT
This incident affected: VPS Infrastructure - US West.