At Risk - Everest Reading - Scheduled UPS Maintenance - 'B' Side
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Jun 10, 2017 - 16:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 10, 2017 - 08:00 BST
Scheduled
Everest Reading have informed us some scheduled UPS Maintenance will be conducted on Sat 10th June 2017 between 08:00 BST and 16:00 BST.

During the maintenance, the 'B' side UPS will be put into maintenance bypass, which means the 'B' feed will be fed power directly, bypassing the UPS and hence without battery backup. The 'A' supply will be unaffected during this period.

No interruption to service is expected, but due to the nature of the works we are classifying this period as 'at risk' with a reduced level of redundancy. We recommend customers ensure all equipment is fed from both the 'A' and 'B' feeds to minimise this risk.

If you have any queries, please do not hesitate to contact us quoting the ticket reference number EMW-057816.
Posted May 12, 2017 - 13:39 BST